pbc825
Structural
- May 21, 2013
- 103
I've been contracted to provide repair recommendations for a retaining wall between two residential properties. The retaining wall is constructed from CMU's that are filled with cement or grout. I didn't see any reinforcing steel poking out of the top under the caps. There are no drawings of the wall or the foundation systems for the two neighboring buildings. The highest differential soil height is about 60 inches. The worst angle from plumb is about 10 degrees which coincides with the maximum differential soil height. I'm contracted by the west property owner, and the east property owner is quite upset.
Wall is about 10 years old and recently a contractor compacted soils on the east side for a paving stone walkway.
The east neighbor is unwilling to do or agree to anything useful, so tying the top of the wall, pinning and excavating for a new properly designed cantilever wall, etc. is out of the question. As is doing anything to disturb the east property. The distance between the two building walls is about 8 ft and the eave overhang is about 2 ft. The plan as I've conceived it so far is to twist in screw piles (haven't decided on the spacing or pile details yet) and hammer down segments of steel plate. Complications include:
1. Headroom to the bottom of the eave is about 10 ft, so extensions will be required. Extension connections may interfere with wall plates.
2. I've never recommended this sort of repair before, so I have little experience with the execution of such a project.
3. Not sure if we'll have trouble driving the plates in with such little headroom.
I'm seeking advice on a few things.
A. Does anyone have experience with this sort of challenge with similar constraints? If so, what repair recommendations did you suggest?
B. Has anyone made a screw pile and driven plate wall? If so, what were the execution challenges?
Thank you in advance for any advice or wisdom.
PBC
Wall is about 10 years old and recently a contractor compacted soils on the east side for a paving stone walkway.
The east neighbor is unwilling to do or agree to anything useful, so tying the top of the wall, pinning and excavating for a new properly designed cantilever wall, etc. is out of the question. As is doing anything to disturb the east property. The distance between the two building walls is about 8 ft and the eave overhang is about 2 ft. The plan as I've conceived it so far is to twist in screw piles (haven't decided on the spacing or pile details yet) and hammer down segments of steel plate. Complications include:
1. Headroom to the bottom of the eave is about 10 ft, so extensions will be required. Extension connections may interfere with wall plates.
2. I've never recommended this sort of repair before, so I have little experience with the execution of such a project.
3. Not sure if we'll have trouble driving the plates in with such little headroom.
I'm seeking advice on a few things.
A. Does anyone have experience with this sort of challenge with similar constraints? If so, what repair recommendations did you suggest?
B. Has anyone made a screw pile and driven plate wall? If so, what were the execution challenges?
Thank you in advance for any advice or wisdom.
PBC