Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Restart control

Status
Not open for further replies.

somebodyfromworld

Mechanical
Jul 15, 2015
35
Hello people

Could anyone of you explain how to use restart control options for combining two different loads:
1. at first load step the construction should move 0,2mm
2. then it is subjected with a pressure

Please look at the pictures with the setting, there is a test cell. Green and Red internal parts should move 0,2mm and 0,387mm respectively from right to left in the test cell and then the pressure must be applied in the right side of the test cell.

deform_hzhftw.png

disp_1_x2bfg9.png

disp_2_tes3bn.png

pressure_eijs92.png

step_usrwgv.png
 
Replies continue below

Recommended for you

Hi
You may generate two load cases. I think first one (moving structure by 0.2mm) should converge easily. The second one wherein there should be non linear contacts, you need to generate manual restart points. I prefer to use equally spaced point generation. Once it is not converging, you may go to contact settings-->change parameters and then use the Solution tab to restart from the last solved substep.

Regards,
Rajendra
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor