Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations IDS on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Retaining wall + ADA switchback ramp

Status
Not open for further replies.

richcrow1

Civil/Environmental
Jul 20, 2007
9
I started this another thread but a friend thought it belonged more over here. Hopefully I can continue the great help I've been getting.

Other Thread:

At this point I don't know how to structuraly connect the retaining wall to the ADA switchback ramp? Calculate the friction factor as one piece? How to attach the dead load of the ramp to the retaining wall? That a lone can make a difference in the calcs.

I've attached a cad drawing to show if better or it might even help someone save time in the future.

With ADA guidelines being implemented more and more. I see this being a very intereseting topic.

Thank you and hope you all are having a good holiday start.

~Rich~

If this is in the wrong section i apologize. Any recommendations to which section is appreciated.
 
Replies continue below

Recommended for you

If the retaining wall is to extend up past the ramp slab to form the railing, then the ramp slab is just an inclined sidewalk and the retaining wall needs to be designed for the surcharge and the lateral load required by code due to the handrail (usually 50 lb/ft or 200 lb concentrated). If the retaining wall does not extend up past the ramp slab, then I would expect to see the slab overhang the retaining wall a couple of inches. Retaining wall is sloped to match ramp slope, fill is compacted well, ramp is placed on top of fill and extends over top of retainig wall. We usually thicken the slab over the retaining wall to 6" or 8". Guard rail and hand rail is attached to ramp slab.
 
I envisioned the retaing wall matching top elevation or exstending by a couple of inches.(being rectangular) Then having the ramp start from elev. 15' to 12' 8" (five foot landing), then ramp from 12'8" to 10'4" (five foot landing) then ramp from 10'4" to existing 9'. Then on both sides have gravity walls coming down triangular shaped to meet elev. 15' to 9'.

Is that sounding about right?

Thanks Twinnell. You sparked a good idea.

And thanks to the rest of you for ideas.

~Rich~
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor