Hi ALL
I am designing a cantilever wall which supposed to retain 6.3 m height of soil from both sides, but one side is to be back filled directly while the other is taking time maybe a year.
i designed for the worst case( in terms of stability) which is active pressure only.. but when i check the active with passive pressures the base slab reinforcement was shocking !?
please share me your opinions about the worst case for design and the reason why the base slab moments doubled ?
I have uploaded the analysis
I am designing a cantilever wall which supposed to retain 6.3 m height of soil from both sides, but one side is to be back filled directly while the other is taking time maybe a year.
i designed for the worst case( in terms of stability) which is active pressure only.. but when i check the active with passive pressures the base slab reinforcement was shocking !?
please share me your opinions about the worst case for design and the reason why the base slab moments doubled ?
I have uploaded the analysis