The top slab with webs of a box girder is to be poured over prepoured concrete slab in such a way that the whole concreting for this 52 m span bridge supported over truss type scaffolding spanning between the piers is completed before any concrete starts setting to avoid putting any stress in the concrete.
The estimated pouring time for the concrete is about 8 hours and the setting time is 4.15 hours.
Some type of retarder can be used. Please advise the right type of retarder or some alternative method to keep the poured concrete green until all concrete is poured in about 8 hours.
The estimated pouring time for the concrete is about 8 hours and the setting time is 4.15 hours.
Some type of retarder can be used. Please advise the right type of retarder or some alternative method to keep the poured concrete green until all concrete is poured in about 8 hours.