Dear All,
With reference to the above subject I would like to raise my query.
I have one stiffener attached to the shell portion which is very near to the shell-cone juncture, i.e. approx. 10mm. Here should I do any NDE procedure for the cone to shell juncture ?
As I understand that according to ASME stiffener can be located at the juncture & there is nothing restricting to do NDE for Butt weld- fillet weld joint.
Kindly share your views.
Warm Regards,
Bikas