prmmel
Civil/Environmental
- Oct 17, 2005
- 34
I have a proeject with about 4000 linear feet of 3" conduits that my client wants to pull the hose through the conduit as the conduit is laid in the ground vs. completing the piping project and pulling the hose later. There contention is that 2-3 of the runs are 300-400 feet each and it will be too difficult to pull the hoses in the pipe after the pipe is installed becasue there are 3 or 4 90s in the runs.
The realistic fact is that they think they are saving time by snaking as they are going....Messy and just a poor application in my opinion.
Any opinions are greatly appreciated. The pipe is sch 40 PVC with electrical sweeping elbows. Each pipe will contain (1) 3/4" OD hose and (1) 1" OD hose. Quite a lot of room.
My concerns:
Getting PVC glue on the hose
dirt on the hose which will cause problems later when they need to be replaced.
Please advise.
Thanks,
Mel
The realistic fact is that they think they are saving time by snaking as they are going....Messy and just a poor application in my opinion.
Any opinions are greatly appreciated. The pipe is sch 40 PVC with electrical sweeping elbows. Each pipe will contain (1) 3/4" OD hose and (1) 1" OD hose. Quite a lot of room.
My concerns:
Getting PVC glue on the hose
dirt on the hose which will cause problems later when they need to be replaced.
Please advise.
Thanks,
Mel