Dear All,
I am currently working on design of sanitary sewage collection systems for an upcoming industry and have no great idea for the same. The industry is spread over 4km by 4 km and source of sewage generation is also quite spread out over entire area. It is proposed to be collected and treated in a Centralized Sewage treatment Plant. The site has water table around just 4 m from ground level. Providing a common gravity sewer line makes it too deep, and may not be recommended
We are planning to provide combination of gravity and pumped mains. Around 6-8 pumping stations are anticipated. which will collect sewage from closeby areas under gravity. Now , each pumping station if feeding to another pumping station(...cascading...)which in turn feed other and finally feeds to Centralized treatment. The max sewage generation per day would not be more than 1000 m3/day
Could you please advise if this concept Okay from your experience. or what is generally being practiced in an industry.
a) Can there be one forced main and each pumping station pumps connects to that main.
b) Whether individual pipes from various lifting stations to central plant would be a better idea.
I am currently working on design of sanitary sewage collection systems for an upcoming industry and have no great idea for the same. The industry is spread over 4km by 4 km and source of sewage generation is also quite spread out over entire area. It is proposed to be collected and treated in a Centralized Sewage treatment Plant. The site has water table around just 4 m from ground level. Providing a common gravity sewer line makes it too deep, and may not be recommended
We are planning to provide combination of gravity and pumped mains. Around 6-8 pumping stations are anticipated. which will collect sewage from closeby areas under gravity. Now , each pumping station if feeding to another pumping station(...cascading...)which in turn feed other and finally feeds to Centralized treatment. The max sewage generation per day would not be more than 1000 m3/day
Could you please advise if this concept Okay from your experience. or what is generally being practiced in an industry.
a) Can there be one forced main and each pumping station pumps connects to that main.
b) Whether individual pipes from various lifting stations to central plant would be a better idea.