builditnow
Civil/Environmental
- Oct 1, 2004
- 5
looking for experience and an opinion on a question from a colleague. A 16 ft deep 8" PVC SS was replaced due to the original installation (over 10 years ago) settling in a 70 ft long area (6" settlement). Ground water is normally 2 ft above the pipe. Pipe was bedded and backfilled full depth with aggregate. The problem: about 1.5 months (recently) after the replacement installation the pipe settled 6" for a second time. The replacement was constructed during dry weather period with no ground water. The pipe is currently uncovered and the groundwater is 2 feet above the pipe. A 3 acre lake is about 500 to 800 feet away form this line. Pipe is about 2 feet below the lake surface water elv. A test pit below pipe subgrade (4ft deep + additional 2 feet of excavator bucket penetration) has revealed no stable soil, the soil is a black shale that is severely weathered. Since the trench is open, in a residential area and roadway we have limited time for hypothesizing. Concrete cradling is possible but we must have a reasonable soil bearing capacity, soil cement - same concern, hanging cradle? This small Town has limited financial capacity and the current alternative suggested by the contractor is concrete piers spaced at small intervals with Ductile Iron Pipe and mechanical joints. Unless founded on stable ground none of these options work. ANy experience out there with similar projects. THANKS