JohnWeal
Mechanical
- Dec 16, 2012
- 124
Hello all,
We have the following defined flows for sewage screened to 6mm (perforated plate)
Daily average flows: 7000 m3/h
Peak hourly to full treatment: 19,000 m3/h
Minimum: 2100 m3/h
The min / max velocities allowable by the client are 0.75 and 1.8 m/s respectively.
Based on the max flow this equates to a 2m diameter pipeline.
For minimum flows the velocity in the 2m pipeline is 0.19 m/s. Clearly well below the minimum required of 0.75m/s.
For average daily flows the velocity is 0.62 m/s. The average daily flows still not enough to move 5e solids along at the minimum velocity required.
Therefore proposing 2 pipelines at 1.5m each to give same cross sectional area. For average flows up one pipe is 1.1 m/s which is acceptable.
For minimum flows up one pipe is 0.33 m/s. Not really acceptable but if average daily flows produce a 1.1 m/s velocity then should be enough to move things along without scepticity.
So on that last point, if maximum flows are not realised for some time, I assume the pipelines would need to be switched over each 24 hours to flush?
Has anyone had any similar flow design scenarios similar to what I have described and any construction/ operation/ maintenance advice would be much appreciated.
Regards
John
We have the following defined flows for sewage screened to 6mm (perforated plate)
Daily average flows: 7000 m3/h
Peak hourly to full treatment: 19,000 m3/h
Minimum: 2100 m3/h
The min / max velocities allowable by the client are 0.75 and 1.8 m/s respectively.
Based on the max flow this equates to a 2m diameter pipeline.
For minimum flows the velocity in the 2m pipeline is 0.19 m/s. Clearly well below the minimum required of 0.75m/s.
For average daily flows the velocity is 0.62 m/s. The average daily flows still not enough to move 5e solids along at the minimum velocity required.
Therefore proposing 2 pipelines at 1.5m each to give same cross sectional area. For average flows up one pipe is 1.1 m/s which is acceptable.
For minimum flows up one pipe is 0.33 m/s. Not really acceptable but if average daily flows produce a 1.1 m/s velocity then should be enough to move things along without scepticity.
So on that last point, if maximum flows are not realised for some time, I assume the pipelines would need to be switched over each 24 hours to flush?
Has anyone had any similar flow design scenarios similar to what I have described and any construction/ operation/ maintenance advice would be much appreciated.
Regards
John