OzStruct
Structural
- Feb 6, 2017
- 5
Hi All
I have recently designed a project which utilized many screw piers. The project manager got a few quotes to do the piers and we sent the winning pier company out to site before signing the quote to do some test piers, which they did. They designed the piers to hopefully found at 5m depth. First day on site they say the piers are not pulling up at 5m depth and we need to splice the piers and extend them to found at 8m were we are getting the required pile capacity (around 100kN to 150kN). Then after they have installed all the screw piers they turn around and hit my client with a huge cost variation, which he is not very happy about and does not want to pay.
We sent them out to do a test pier so I think they should have known about the soils conditions. We also had a very good geotech report which they have. I know this is more of a project management question but I am curious to know your thoughts. How do we know that the piers didn't pull up correctly at 5m and that the splicing of piers is just an excuse to go for a variation? Also is the client just at the mercy of the pier contractor for the amount of the variation they can claim? Seems very unfair to the client as we all went to great lengths to avoid this happening.
Thanks
I have recently designed a project which utilized many screw piers. The project manager got a few quotes to do the piers and we sent the winning pier company out to site before signing the quote to do some test piers, which they did. They designed the piers to hopefully found at 5m depth. First day on site they say the piers are not pulling up at 5m depth and we need to splice the piers and extend them to found at 8m were we are getting the required pile capacity (around 100kN to 150kN). Then after they have installed all the screw piers they turn around and hit my client with a huge cost variation, which he is not very happy about and does not want to pay.
We sent them out to do a test pier so I think they should have known about the soils conditions. We also had a very good geotech report which they have. I know this is more of a project management question but I am curious to know your thoughts. How do we know that the piers didn't pull up correctly at 5m and that the splicing of piers is just an excuse to go for a variation? Also is the client just at the mercy of the pier contractor for the amount of the variation they can claim? Seems very unfair to the client as we all went to great lengths to avoid this happening.
Thanks