JEDClampett and other Concrete clarifier folks,
Can anyone enlighten me on where the "38,000 lb-ft" of moment comes from in section 13 of the thread title book (on page 16, second paragraph)? Seems like it just was pulled out of thin air to use in the example.
I've got a 20' diameter, 14' tall clarifier with the slab/wall tied together. I'm trying to use this guide since it's my first clarifier rodeo, but am stuck on where that number comes from.
Thanks!
Nick
Can anyone enlighten me on where the "38,000 lb-ft" of moment comes from in section 13 of the thread title book (on page 16, second paragraph)? Seems like it just was pulled out of thin air to use in the example.
I've got a 20' diameter, 14' tall clarifier with the slab/wall tied together. I'm trying to use this guide since it's my first clarifier rodeo, but am stuck on where that number comes from.
Thanks!
Nick