See tasks that are affected when a date changes

Status
Not open for further replies.

lavaghman

Computer
Jun 12, 2007
4
Hi there

Have a large project plan and need to change a couple of dates by a week. I want to easily see all other tasks that are impacted when I change this date. I thought there was a setting that highlights the affected tasks, but unfortunatly can't find it for the life of me!

Would appreciate your help

Many Thanks,
J
 
Replies continue below

Recommended for you

Actually found it! - Called change highlighting. Can be switched on or off using View from menu and "show change highlighting"
 
Hi J

If you have 'predecessors' defined in your project schedule then the relationship of the change(s) to other tasks would automatically display.

Regards,
Dora