Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations pierreick on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Seismic Connection to Pile Cap

Status
Not open for further replies.

arbitrader

Mechanical
Nov 7, 2000
26
I am planning to utilize precast concrete piles for a foundation in Seismic Design Category C and IBC 1807.2.23.1.1 requires concrete piles to be connected to the pile cap by embedding the pile reinforcement or field placed dowels anchored in the pile cap for a distance equal to the development length.

Field placing dowels make sense if it was a concrete filled pipe pile but a little labor intensive to drill and epoxy hundreds of precast concrete piles.

Can anyone offer their experiences in making this connection with a precast prestressed pile without using longer piles and breaking up pile to expose tendons?

 
Replies continue below

Recommended for you

Detail the top of pile with embedded rebar connectors such as Lenton?
 
JAE thanks for the suggestion, but I don't think that will work. After piles are driven to capacity, pile tops have to be cut off to proper elevation.
 
Any pile in SPC C, should be embedded at least 18" and thus should have ample room for connection hardware/rebar.

I didn't get this from a code, just experience.

Regards,
Qshake
[pipe]
Eng-Tips Forums:Real Solutions for Real Problems Really Quick.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor