hondashadow1100vt
Civil/Environmental
- Dec 30, 2008
- 108
Hi all,
Brainstorming some ideas for a pump station to permit pump downsizing pumps (ideally with minimal future work) in the future when a new larger force main comes on line.
Scenario: Pump station capacity expansion that operates on an existing undersized force main (FM) line (currently about ~10-ft/sec peak. Too high.). FM needs to be upsized. Pump type proposed (and favored) as dry pit submersible end suction non-clog type. Need to build the pump station first and operate it on the existing undersized FM, then build & connect to the FM 5-10 years later (or possibly never). Using the existing force main, the friction head and HP required to pump through the existing is significantly greater than the future upsized force main condition. With the the aim of trying to ideally avoid a second construction contract to renovate the pump station guts when the new FM becomes available, the following list of ideas comes to mind initially (quality and practicability varies):
- VFD (client has a serious aversion to VFDs. Very old school.)
- Replace the motor later with slower speed (requires construction work, realignment/rebalancing)
- Provide two speed motor (likely highly custom for submersible motor)
- replace impellers with smaller diameter impeller later (requires some serious work, realignment/rebalancing)
- Change pump type to extended shaft pumps and go with resistor banks with speed settings (I.e., simply switch the speed setting in the future)
- Change pump type to extended shaft pumps and go with eddy current variable speed drives (have not done this one)
- Install discharge header control valve (maybe a V-port ball valve) on the discharge. For existing small FM, operate with valve open, for future “right sized” FM throttle valve (or valves) to add friction head to system. (waste of operating dollar$)
- Install orifice plate in the discharge when the future “right sized” FM line comes online (waste of operating dollar$)
- Replace the pumps when the new force main becomes available (requires construction work)
- Operate on fewer pumps when the new force main becomes available
- Swap out gearbox (requires construction work)
Are there any other ideas out there that I have overlooked?
I welcome any ideas and any critiques of the above “good ideas” (...and the not so good ones).
Thanks all!
Brainstorming some ideas for a pump station to permit pump downsizing pumps (ideally with minimal future work) in the future when a new larger force main comes on line.
Scenario: Pump station capacity expansion that operates on an existing undersized force main (FM) line (currently about ~10-ft/sec peak. Too high.). FM needs to be upsized. Pump type proposed (and favored) as dry pit submersible end suction non-clog type. Need to build the pump station first and operate it on the existing undersized FM, then build & connect to the FM 5-10 years later (or possibly never). Using the existing force main, the friction head and HP required to pump through the existing is significantly greater than the future upsized force main condition. With the the aim of trying to ideally avoid a second construction contract to renovate the pump station guts when the new FM becomes available, the following list of ideas comes to mind initially (quality and practicability varies):
- VFD (client has a serious aversion to VFDs. Very old school.)
- Replace the motor later with slower speed (requires construction work, realignment/rebalancing)
- Provide two speed motor (likely highly custom for submersible motor)
- replace impellers with smaller diameter impeller later (requires some serious work, realignment/rebalancing)
- Change pump type to extended shaft pumps and go with resistor banks with speed settings (I.e., simply switch the speed setting in the future)
- Change pump type to extended shaft pumps and go with eddy current variable speed drives (have not done this one)
- Install discharge header control valve (maybe a V-port ball valve) on the discharge. For existing small FM, operate with valve open, for future “right sized” FM throttle valve (or valves) to add friction head to system. (waste of operating dollar$)
- Install orifice plate in the discharge when the future “right sized” FM line comes online (waste of operating dollar$)
- Replace the pumps when the new force main becomes available (requires construction work)
- Operate on fewer pumps when the new force main becomes available
- Swap out gearbox (requires construction work)
Are there any other ideas out there that I have overlooked?
I welcome any ideas and any critiques of the above “good ideas” (...and the not so good ones).
Thanks all!