Roxbury
Structural
- Aug 24, 2023
- 1
We are facing a costtly problem and advice is needed. In upstate NY, we have a level site, elevation 100', that has about 3' of miscellaneous fill consisting of boulders, rock, concrete pieces, and general soils. Underneath this stratum is a 2' stratum of dark, organic soil, top soil. Underneath this organic stratum, we have load bearing, 4 kips/SF, sandy soil.so, this load bearing stratum is about 5' below the existing grade.
The entire site is to be raised 4' with controlled structural fill to elev 104' Loads are for a 4-story self-storage building with a load bearing partition system. DL + LL = 7,0000 plf along the 1st floor's load bearing partitions, which are spaced 10' o.c.
The pad is 30,000 SFG. Excavating the entire pad 4' deep (4,444 CY) to reach reach the bearing stratum is costly. In addition to this 4' deep excavation, the pad will then need to be backfield with controlled structural fill - - - a depth of 4' and then another 4' of structural fill will be placed on top to realize the FF of elev of 104'.
Questions: Do we need to excavate down to remove the underlying 2' thick organic stratum under the pad area, or can we just add the additional, required 4' of structural, controlled fill on top of the existing grade and then design say a 10" floating mat slab to take the partition LF loads and the 125 psf 1st floor LL?
The entire site is to be raised 4' with controlled structural fill to elev 104' Loads are for a 4-story self-storage building with a load bearing partition system. DL + LL = 7,0000 plf along the 1st floor's load bearing partitions, which are spaced 10' o.c.
The pad is 30,000 SFG. Excavating the entire pad 4' deep (4,444 CY) to reach reach the bearing stratum is costly. In addition to this 4' deep excavation, the pad will then need to be backfield with controlled structural fill - - - a depth of 4' and then another 4' of structural fill will be placed on top to realize the FF of elev of 104'.
Questions: Do we need to excavate down to remove the underlying 2' thick organic stratum under the pad area, or can we just add the additional, required 4' of structural, controlled fill on top of the existing grade and then design say a 10" floating mat slab to take the partition LF loads and the 125 psf 1st floor LL?