Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Setbacks Between Retaining Walls to Allow for Passive Pressure 1

Status
Not open for further replies.

Geo Strata-gist

Geotechnical
Aug 13, 2024
1
Background: I am working on a project that proposes a new retaining wall near an existing wall (existing wall is the property line wall). The max retained height of the existing wall is around 6 ft. Generally granular backfill and foundational soils. The Architect would like to make the new wall as short and as close to the existing wall as possible without surcharging the existing wall. The structural proposed offsetting the new wall based on a 1:1 line starting from the bottom of footing (existing wall) to the bottom of footing (new wall) [see the sketch he provided below]

Sketch_from_designer_cyt2lw.png


The structural informed me that the design was failing in sliding without passive resistance. He wants to know what percentage of the passive pressure he can apply to the key and footing of the wall. I figure the wall would basically need to be embedded below the intercept between the active and passive wedges [see schematic below].

Wall_embedment-offest_schematic_pre9dg.png


Question 1: How would you guys go about this problem? I understand that passive pressures will generally dissipate in an infinite idealized soil profile (typically at around 2-2.5 times the embedment depth at the from the wall (similar to experimental findings Link); however, I am unsure how they would translate into lateral surcharge pressures on the existing wall. Any resources on that?

Question 2: If the existing wall has a decent amount of toe embedment at the face (more than needed to resist the existing retained fill in its original state), can the new wall be placed in the active wedge of the old wall and rely on the available (non-mobilized) passive pressures at the front of the existing wall? (Assuming the wall can resist the surcharge from a structural perspective). Hopefully that makes sense.

Thank you!
 
Replies continue below

Recommended for you

I think it would help to locate the key towards the back of the heel rather than at the toe.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor