I am involved with an interesting project.....
A client wants to build light structures for energy generation on large 40+ hectare area 60m high decommisioned gold tailingsdams (slimesdams).
The dams have only recently been decommisions and although the surface is dry the dam below is still very wet.
How would one go about calculating the settlement over time of the structure?
I first want to determine if the project is feasable before I allow detailed investigation.
Anny and all feedback will be appreciated.
I am involved with an interesting project.....
A client wants to build light structures for energy generation on large 40+ hectare area 60m high decommisioned gold tailingsdams (slimesdams).
The dams have only recently been decommisions and although the surface is dry the dam below is still very wet.
How would one go about calculating the settlement over time of the structure?
I first want to determine if the project is feasable before I allow detailed investigation.
Anny and all feedback will be appreciated.