I was calculating out my surface loading rate for my solids contact basin to see if we actually fell within the state regulation on SLR. We did under NJ rule running at 700gpm/1962ft2 = 0.356 gpm/ft2. I decided to go a step further and find out what the settling velocity was but using the equation I have does not bring me anywhere close to what range it should be, 1 to 3 cm/min. I don't think the equation I'm following is written correctly. If someone could clarify this it would be appreciated.
gpd/ft2 x 3785 cm3/gal x 1ft2/929 x 1 day/1440 min = cm/min
gpd/ft2 x 3785 cm3/gal x 1ft2/929 x 1 day/1440 min = cm/min