Hi all,
Here is a question I've been trying to find an answer for. I attached a sketch to clarify.
ACI 318-11 Section 7.10.5.7 requires you to have ties in the top 5" of a column (or pier) to "improve load transfer from the anchor bolts to the column or pier..."
ACI3 318-11 Appendix D.4.2.1 says where anchor reinforcement is provided in accordance with D.6.2.9, breakout can be neglected and the steel is designed to carry the load.
My question is, can the ties required by 7.10.5.7 be designed to carry the load in accordance with D.6.2.9 for the situation in the attached sketch?
Thank you for any advice.
Here is a question I've been trying to find an answer for. I attached a sketch to clarify.
ACI 318-11 Section 7.10.5.7 requires you to have ties in the top 5" of a column (or pier) to "improve load transfer from the anchor bolts to the column or pier..."
ACI3 318-11 Appendix D.4.2.1 says where anchor reinforcement is provided in accordance with D.6.2.9, breakout can be neglected and the steel is designed to carry the load.
My question is, can the ties required by 7.10.5.7 be designed to carry the load in accordance with D.6.2.9 for the situation in the attached sketch?
Thank you for any advice.