Is there an allowance or duration increase allowed in shear capacity when designing a wood moment frame in place of a shear wall (with wind only) for either the top plates or header such as the 1.4 allowed in panels per IBC section 2306.3.2?
Example, SYP #2 has a value of 90 psi. Can this be increased for a wind only collector and if so how much (1.4, 1.33, 1.6)?
Any opinions or thoughts are appreciated.
Thanks !
Example, SYP #2 has a value of 90 psi. Can this be increased for a wind only collector and if so how much (1.4, 1.33, 1.6)?
Any opinions or thoughts are appreciated.
Thanks !