I'm designing a 4-story wood framed building using RISA software. For the shear walls, the program offers various tension straps to transfer chord forces where required. I'm curious how a tension strap would get installed on an interior shear wall since the plywood floor deck would conflict with the strap.
I would think the strap would have to be installed prior to the floor deck, or a slit cut in the deck after, to pass the strap thru, both seem cumbersome …. maybe it would just be easier to use a small holdown above an below the floor deck and drill a hole for a tie rod ---- any advise … tank you
I'm designing a 4-story wood framed building using RISA software. For the shear walls, the program offers various tension straps to transfer chord forces where required. I'm curious how a tension strap would get installed on an interior shear wall since the plywood floor deck would conflict with the strap.
I would think the strap would have to be installed prior to the floor deck, or a slit cut in the deck after, to pass the strap thru, both seem cumbersome …. maybe it would just be easier to use a small holdown above an below the floor deck and drill a hole for a tie rod ---- any advise … tank you