I'm working on a job where they will be removing the lower three courses of brick in order to do concrete spall repair work. We need to shore the existing bricks above. Normally, we would recommend a temporary relieving angle anchored into the backup masonry. However, the wall is made up of (1) wythe face brick and the backup is CMU. Anyone have recommendations on how to go about shoring this? Attached are section and elevation view of removal work.