Kimosabi
Aerospace
- Mar 7, 2003
- 3
I've heard this is not possible in Microsoft Project. I would like the progress bar that is within my summery bar to stop at the last complete milestone (which has been rolled up to the summery bar). As it stands, Project will only add up the percentages complete and apply an overall average completion to the summery bar. I have the milestones showing complete when they are designated as 100 percent, but I would like the progress bar within the summery bar to be based on those completions. Any way possible?