Hello,
I have 690V network, 3 phase system, no neutral, with 2400Amps load current.
I end up with 8 runs of 3 core 240mm2 cable size.
When I select 1 core cable, I can manage with 12 runs. It means only 4 runs per phase.
3 core cable in general has low current capacity than single core.
Is that possible? or am I doing something wrong?
regards
Avi.
I have 690V network, 3 phase system, no neutral, with 2400Amps load current.
I end up with 8 runs of 3 core 240mm2 cable size.
When I select 1 core cable, I can manage with 12 runs. It means only 4 runs per phase.
3 core cable in general has low current capacity than single core.
Is that possible? or am I doing something wrong?
regards
Avi.