gvasiliou
Electrical
- Mar 24, 2012
- 41
Hi guys,
I'm George, kind of newbie in this forum and i would like some of your help, if this ok with you.
The Project: To determine the bolted L-G SCC, in a generator parallel to the grid configuration.
The Problem:
My hand calculations can not verify the results of the SC software used (ETAP).
I'm trying to verify Bolted LG SCC using MVA method and even calculating impedances (z) in per unit system using symmetrical components analysis.
In all cases, i can verify the overall SCC (85,8 kA at 400Volts bus 3) but i'm not able to verify that SCC coming from Generator is 46 kA and SCC coming from the Grid is 40,5 kA (this numbers are given by ETAP Software).
Anybody that could "play" with my system to advise if he is able to "verify" ETAP results (46 and 40.5 kA respectivelly)?
I have upload a file showing the system single line drawing with ETAP Results, the tech data used by ETAP to perform calculations acc to IEC909, and my hand notes proving the total L-G SCC at bus 3 , equals to 85,8kA (close to 86,4 of ETAP).
Thanks in advance for your support in this ball breaking issue.
George V - Hellas 2012
I'm George, kind of newbie in this forum and i would like some of your help, if this ok with you.
The Project: To determine the bolted L-G SCC, in a generator parallel to the grid configuration.
The Problem:
My hand calculations can not verify the results of the SC software used (ETAP).
I'm trying to verify Bolted LG SCC using MVA method and even calculating impedances (z) in per unit system using symmetrical components analysis.
In all cases, i can verify the overall SCC (85,8 kA at 400Volts bus 3) but i'm not able to verify that SCC coming from Generator is 46 kA and SCC coming from the Grid is 40,5 kA (this numbers are given by ETAP Software).
Anybody that could "play" with my system to advise if he is able to "verify" ETAP results (46 and 40.5 kA respectivelly)?
I have upload a file showing the system single line drawing with ETAP Results, the tech data used by ETAP to perform calculations acc to IEC909, and my hand notes proving the total L-G SCC at bus 3 , equals to 85,8kA (close to 86,4 of ETAP).
Thanks in advance for your support in this ball breaking issue.
George V - Hellas 2012