I have a client interested in constructing a septage treatment facility that would include dewatering presses and pumping resultant liquid component about 180 feet (vertical head) up a hill to some leaching fields.
He has a great property for it except 3-phase does not come to his property, and is way too far away to realistically have the power company extend it.
He's been told the best way to go is by getting two diesel 3-phase generators. Two so that he'll have back-up when the other is being serviced. Seems an expensive option to me.
I was curious how the single-phase to 3-phase converter's operated from an efficiency and cost standpoint. Does anyone have experience with these? Are they really that inefficient and expensive to run?
He has a great property for it except 3-phase does not come to his property, and is way too far away to realistically have the power company extend it.
He's been told the best way to go is by getting two diesel 3-phase generators. Two so that he'll have back-up when the other is being serviced. Seems an expensive option to me.
I was curious how the single-phase to 3-phase converter's operated from an efficiency and cost standpoint. Does anyone have experience with these? Are they really that inefficient and expensive to run?