skeletron
Structural
- Jan 30, 2019
- 846
I usually put 3 boiler plate items in my Foundation General Notes. The first item states (paraphrase) that the Client is responsible for retaining a geotechnical engineer to provide foundation design specifications/recommendations prior to starting construction. The second item states (paraphrase) my expectations for the geotechnical engineer report (ie. site class, bearing, backfill, etc., field review, letter of assurance). The third item states (paraphrase) that "In lieu of available geotechnical specifications, the structural design has assume the following parameters based on typical minimum standards..." and then lists some pretty standard items (bearing pressure used, depth of foundation, etc).
My current project is a single-storey home. Contractor is replacing walls with full side doors, so there are now point loads instead of distributed loads. I was engaged after the contractor got a stop-work order. The backside of a family's house is basically open while they wait for permitting to proceed (not my problem, but damn do I feel sorry for them).
Based on existing maps from the District, I can expect that the ground is soft-sand. My calculations have assumed the worst-case based on the prescriptive values. I've also gone through a couple iterations of what the existing soil pressures were and they seem to jive with the prescriptive values (say max 1000psf). I have designed pad footing extensions to suit this assumed bearing pressure.
The AHJ has now flagged this project and is telling the Contractor that they may need to involve a geotech because of the notes on the structural drawings, and also because there is potential that the District inspector may flag it during there own inspection. The Contractor does not seem to want to engage a geotech (I've provided 2 referrals). Can't tell if this is a cost thing or a "we can't wait another 2-3 weeks to close-up thing" kind of thing. So...
MY QUESTION FOR DISCUSSION
1. Can I provide a written memo to the contractor outlining the risks that they will assume (ie. unknown settlement due to new point loads) by not engaging a geotech and then revise my drawing notes to suit? Basically put wording that kind of waives my liability if there is future drywall cracking or sliding door misalignment due to settlement...
2. Tell the Contractor to *pound sand* (excuse the pun) and get a geotech.
3. Add a field review, assess the ground using the unscientific "I can't shovel the ground anymore" method, and eat a bit of the risk.
4. Don't even worry about it and just revise the drawings to proceed.
I remember there was a similar thread within the last year regarding a similar general subject. So, I'm wondering how others would handle this in practice.
MY INITIAL THOUGHT
Logically, I want to go with #1 but I'm not really sure how enforceable any of that is. Family gets to have their home buttoned up, Contractor gets to complete the work, AHJ no longer has notes to flag the project. This option probably runs in tandem with #3 by default.
In any professional practice resource, the recommendation would probably be to not even take on the project or else go with #2 but I don't practically see this happening with single-family home renovations in my area.
My current project is a single-storey home. Contractor is replacing walls with full side doors, so there are now point loads instead of distributed loads. I was engaged after the contractor got a stop-work order. The backside of a family's house is basically open while they wait for permitting to proceed (not my problem, but damn do I feel sorry for them).
Based on existing maps from the District, I can expect that the ground is soft-sand. My calculations have assumed the worst-case based on the prescriptive values. I've also gone through a couple iterations of what the existing soil pressures were and they seem to jive with the prescriptive values (say max 1000psf). I have designed pad footing extensions to suit this assumed bearing pressure.
The AHJ has now flagged this project and is telling the Contractor that they may need to involve a geotech because of the notes on the structural drawings, and also because there is potential that the District inspector may flag it during there own inspection. The Contractor does not seem to want to engage a geotech (I've provided 2 referrals). Can't tell if this is a cost thing or a "we can't wait another 2-3 weeks to close-up thing" kind of thing. So...
MY QUESTION FOR DISCUSSION
1. Can I provide a written memo to the contractor outlining the risks that they will assume (ie. unknown settlement due to new point loads) by not engaging a geotech and then revise my drawing notes to suit? Basically put wording that kind of waives my liability if there is future drywall cracking or sliding door misalignment due to settlement...
2. Tell the Contractor to *pound sand* (excuse the pun) and get a geotech.
3. Add a field review, assess the ground using the unscientific "I can't shovel the ground anymore" method, and eat a bit of the risk.
4. Don't even worry about it and just revise the drawings to proceed.
I remember there was a similar thread within the last year regarding a similar general subject. So, I'm wondering how others would handle this in practice.
MY INITIAL THOUGHT
Logically, I want to go with #1 but I'm not really sure how enforceable any of that is. Family gets to have their home buttoned up, Contractor gets to complete the work, AHJ no longer has notes to flag the project. This option probably runs in tandem with #3 by default.
In any professional practice resource, the recommendation would probably be to not even take on the project or else go with #2 but I don't practically see this happening with single-family home renovations in my area.