Guest
Is there any "rule-of-thumb" as regards with the size of an automatic power factor correction capacitor banks? I would like to know what is the ratio with respect to the installed transformer kVA capacity against a capacitor bank kVAR capacity - if there is any - without knowing what loads may be connected to the system downstream. That is, the overall system power factor is not yet determined. (Knowing that this is an automatic power factor sensing corrective equipment, the power factor can vary anytime and it shall function proportionally.) And without applying vectorially the sums of effective and reactive power.
I am new in the field and my immediate supervisor says a 25% factor may be used. That is, for example, I have a 1000kVA main transformer in a substation, all I need to do is take 25% of that and the size of the capacitor bank should be 250kVAR at certain number of steps.
Is it practical (as in acceptable to Electrical Engineering practice) to connect this APFC bank at the LV mains (i.e., as one of the main LV switchgear branches)?
Follow-up question(s):
Is it required that, during emergency generator power changeover, the capacitor bank shall be disconnected from the bus (the LV switchgear main mentioned above is an ATS where incoming power comes from a utility via transformer and a standby genset.)
How is the number of steps of a capacitor determined (is there any ruling where a certain size of capacitor module shall be used with a certain number of steps)?
Thanks.
I am new in the field and my immediate supervisor says a 25% factor may be used. That is, for example, I have a 1000kVA main transformer in a substation, all I need to do is take 25% of that and the size of the capacitor bank should be 250kVAR at certain number of steps.
Is it practical (as in acceptable to Electrical Engineering practice) to connect this APFC bank at the LV mains (i.e., as one of the main LV switchgear branches)?
Follow-up question(s):
Is it required that, during emergency generator power changeover, the capacitor bank shall be disconnected from the bus (the LV switchgear main mentioned above is an ATS where incoming power comes from a utility via transformer and a standby genset.)
How is the number of steps of a capacitor determined (is there any ruling where a certain size of capacitor module shall be used with a certain number of steps)?
Thanks.