Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

Slab and wall joints in concrete tank 1

Status
Not open for further replies.

rholder98

Structural
Oct 5, 2005
158
0
0
US
In a liquid-filled tank, must construction joints in the wall align with the construction joints in the slab? These are construction joints, not contraction joints--i.e., continuous reinforcement.

Specifically, this is for a circular tank, and according to the specs, the slab will be placed in six pie-shaped segments, so that the joints align with the joints in the walls, which are limited to 60 feet placement lengths. Why does it matter whether the joints align?
 
Replies continue below

Recommended for you

I would recommend lining them up. If you get a crack at the joint it might continue into the adjoining wall or slab and leak. It won't be a lot of leakage, and it will close up, but it will still be there.
I sometimes have more joints in the walls than slab (usually twice as many), but I still try to match them up where I can.
 
Status
Not open for further replies.
Back
Top