beeth
Mechanical
- Sep 26, 2005
- 2
I am a relatively new mechanical engineer doing mostly plant maintenance work. However I have been assigned the task of designing a slab-on-grade for a pushing a loader along a rock pile.
The slab should be 12'x12' with 2 rails embedded @ 4' feet and centered along the slab.
The loader with max capacity filled bucket weight ~100k
My current design based off of the building the loaders are serviced in includes a 12 inch slab with top and bottom #4 bar spaced at 12". Does this seem reasonable?
My other question is how to deal with the embedded rails. Originally they were only going to be 2 inches deep which I figured would be ok. Almost considered a sawcut.
But now they want to use 6" deep 90# rails mainly because we have them on site. A 6 inch rail embedded in a 12 inch slab seems like a big problem to me.
I haven't dealt with concrete before and don't know too much about design. However I feel fairly confident in the slab holding up to the load, not including the rails.
I appreciate any help. Thank you.
The slab should be 12'x12' with 2 rails embedded @ 4' feet and centered along the slab.
The loader with max capacity filled bucket weight ~100k
My current design based off of the building the loaders are serviced in includes a 12 inch slab with top and bottom #4 bar spaced at 12". Does this seem reasonable?
My other question is how to deal with the embedded rails. Originally they were only going to be 2 inches deep which I figured would be ok. Almost considered a sawcut.
But now they want to use 6" deep 90# rails mainly because we have them on site. A 6 inch rail embedded in a 12 inch slab seems like a big problem to me.
I haven't dealt with concrete before and don't know too much about design. However I feel fairly confident in the slab holding up to the load, not including the rails.
I appreciate any help. Thank you.