Mr168
Materials
- Aug 5, 2008
- 731
Please forgive my ignorance on the subject, as I am a welding guy trying to help a fellow QC guy find an answer.
Is it required or outlined in any code as to when slump tests should be performed when Super P plasticizer is used? The concrete had all tests run before adding the Super P, air tested ok, slump was routinely low. These results were documented, the Super P was added, and no additional testing was performed before it was poured.
This is foundation work for a fossil power plant.
We're going under the assumption that the addtion of the Super P would pretty much invalidate any slump test anyways, but we're looking for some evidence or section of code that confirms or refutes this process of running no further tests after the plasticizer is added (break tests were all coming back good).
This is pretty much a CYA scenario in case of a QA audit or something like that. Thanks for the help.
Is it required or outlined in any code as to when slump tests should be performed when Super P plasticizer is used? The concrete had all tests run before adding the Super P, air tested ok, slump was routinely low. These results were documented, the Super P was added, and no additional testing was performed before it was poured.
This is foundation work for a fossil power plant.
We're going under the assumption that the addtion of the Super P would pretty much invalidate any slump test anyways, but we're looking for some evidence or section of code that confirms or refutes this process of running no further tests after the plasticizer is added (break tests were all coming back good).
This is pretty much a CYA scenario in case of a QA audit or something like that. Thanks for the help.