Hi everyone, I have this doubt, when we are detailing a Beam-Column Joint at roof level in a SMF, whats the proper way to do it? The literature that I have read, doesnt show this kind of case and the ACI doesnt explicitly tells you how to do it. The longitudinal top reinforcement of the beam should be encased by the longitudinal reinforcement of the column in the joint? is it possible that the longitudinal reinforcement of the column doesnt get to top of roof and just stays below the beam top longitudinal reinforcement for constructability purposes?