BNGeo
Geotechnical
- Nov 28, 2023
- 19
I'm looking at a project that requires excavation to about 25 feet depth over an area of about 20,000 sf, with bedrock at higher than the target depth (let's say rock at 20 feet on average). Groundwater is at about 5 feet. For this scenario, I'm anticipating temporary SOE would be installed to the top of rock (tied back, braced or pinned for stability).
Do you expect that the contractor would find sheet piling to be a good option here? They would not seal at the interface of the sheets/rock (it is hard rock and rock is sloping). So there would be seepage through the sheets/rock interface, as well as whatever seepage through the interlocks.
Also, would it be appropriate to install wellpoints or deep wells for this condition? Would the wells typically go into the bedrock or would they terminate right at the bedrock surface?
The bedrock is mostly RQD~80%, but one of five cores had an anomalous 20% RQD. Add to this that if it is determined to used controlled blasting to remove the rock, there will likely be additional rock fracturing that will increase seepage through the rock.
Thanks!
Do you expect that the contractor would find sheet piling to be a good option here? They would not seal at the interface of the sheets/rock (it is hard rock and rock is sloping). So there would be seepage through the sheets/rock interface, as well as whatever seepage through the interlocks.
Also, would it be appropriate to install wellpoints or deep wells for this condition? Would the wells typically go into the bedrock or would they terminate right at the bedrock surface?
The bedrock is mostly RQD~80%, but one of five cores had an anomalous 20% RQD. Add to this that if it is determined to used controlled blasting to remove the rock, there will likely be additional rock fracturing that will increase seepage through the rock.
Thanks!