gte447f
Structural
- Dec 1, 2008
- 799
Structural guy here with a few questions. Thanks in advance for any advice.
I designed a CMU pier and footing plan for a residential renovation involving adding a second story to an older house. The design was based on an allowable bearing pressure of 1500 psf. Now the contractor has decided to build a continuous CMU foundation wall on a strip footing, which is fine, but when the inspector came out to inspect the footing excavation prior to pouring concrete, he apparently said that the footing subgrade was too soft. So, the contractor proceeded to dig deeper looking for firmer ground. They are now down to 5 ft deep and as much as 7 ft deep in places. The inspector came back out and apparently didn't mention the soft subgrade anymore, so presumably he is satisfied that they have reached firm enough material, but he said, since the footing no longer matches the plans, he needs a revision from the engineer (i.e. me).
I am getting to the point of my question, so thanks for bearing with me. The contractor described to me that the original excavation was soft in the top 2 inches or so, based on sticking a piece of rebar into the soil, but was firm below 2 inches. So they would excavate a couple of inches (with hand tools), but then the next 2 inches would be soft, and so they would repeat the process, until now they are 5-7 ft deep. My question is why is the top 2 inches of the clay in the excavations always soft? Is it because of lack of confining pressure from the soil that has been removed?
Also, they say they have reached firm ground, but I am skeptical that I may arrive onsite to discover the same conditions (i.e. a couple of inches of soft clay in the excavation with seemingly firm material underneath). If so, what should be done? Should gravel be placed in the excavation? If so, how much?
I designed a CMU pier and footing plan for a residential renovation involving adding a second story to an older house. The design was based on an allowable bearing pressure of 1500 psf. Now the contractor has decided to build a continuous CMU foundation wall on a strip footing, which is fine, but when the inspector came out to inspect the footing excavation prior to pouring concrete, he apparently said that the footing subgrade was too soft. So, the contractor proceeded to dig deeper looking for firmer ground. They are now down to 5 ft deep and as much as 7 ft deep in places. The inspector came back out and apparently didn't mention the soft subgrade anymore, so presumably he is satisfied that they have reached firm enough material, but he said, since the footing no longer matches the plans, he needs a revision from the engineer (i.e. me).
I am getting to the point of my question, so thanks for bearing with me. The contractor described to me that the original excavation was soft in the top 2 inches or so, based on sticking a piece of rebar into the soil, but was firm below 2 inches. So they would excavate a couple of inches (with hand tools), but then the next 2 inches would be soft, and so they would repeat the process, until now they are 5-7 ft deep. My question is why is the top 2 inches of the clay in the excavations always soft? Is it because of lack of confining pressure from the soil that has been removed?
Also, they say they have reached firm ground, but I am skeptical that I may arrive onsite to discover the same conditions (i.e. a couple of inches of soft clay in the excavation with seemingly firm material underneath). If so, what should be done? Should gravel be placed in the excavation? If so, how much?