Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations GregLocock on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Soil Nail Design

Status
Not open for further replies.

dpa

Civil/Environmental
Dec 10, 2002
173
I am looking for information to help determine the quantity, spacing and depth of soil nails. The site is a steep slope about 45 to 55 degrees and about 150 feet high. Soil is fine sand with just enough silt to form solid but easily broken lumps when dug with a shovel. Lab tests will be performed later this week.

There is a timber bulkhead on top which varies in height from 10 to 18 feet along a length of 250 feet. The base of the wall is undercut by mountain beaver tunnels.

I know how to figure out the active area behind a typical retaining wall or bulkhead but am a bit fuzzy about the combined geometry of the two active areas (bulkhead plus unrestrained slope).

Thanks,
DPA
 
Replies continue below

Recommended for you

FHWA, Caltrans and University of California Davis all have publications and programs that you can use.
 
Hi RCEJD,

Thanks I'll check them out.

DPA
 
You have a very large and steep hill. I hope the project geotec has run a slope stability analysis. Were a good subsurface investigation and lab testing performed? Any slope stability analysis or soil nail design is only as good as the accuracy of the subsurface profile and soil or rock design properties.
 
Not yet. Just in the proposal stage

DPA
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor