I recently came across; a GRID interconnection study that some engineers from out ETC Transmission utility did for a client. However; they quoted a formula from the book: "Jeurgen Schlabbach and Karl-Heinz Rafalki Power System Engineering" and indicated that; the PV penetration level is dependent on the 5% Rapid voltage change at the PCC; i.e (RVC 5% = MVA PV plant/ SC at PCC). I have not seen this reference in any of modelling guidelines and or standards.
i am confused because; i understood that safe connection of the PV Plant is how stiff the PCC is due to the Effective short circuit ratio is at PCC.
M question is; is their methodology correct? If not what determines the MW connection at a certain PCC?