EngMan40
Civil/Environmental
- Jan 11, 2009
- 65
22 story building is to be constructed with 15 ft deep basement. the structure engineer's original system is temporary soldier pile with timber lagging. after both wall footings and interior foundations are constructed a 12" thick reinforced basement wall will take place at the perimeter beside the soldier piles. the basement wall takes load of about 2 stories only while the major load is taken by interior footings.
The new idea is to make the SOE as permanent, that is to make the soldier piles and timber lagging take the short term loads and then after the excavation is done the reinforced concrete basement wall will be cast in place between soldier piles and becomes as lagging to the long term permanent system. there will be a beam runs on top of the soldier piles and the concrete planks which will provide support for the 2 story loads.
I am trying to compare the two systems:
system (1) temporary shoring system with 12" thick basement wall and basement wall footings
system (2) permanent shoring system with 8" thick basement wall and not basement footings
Note: No tiebacks permitted since there is a nearby basement wall of structure runs 4' away along the property line.
- Do you think there is any savings in foundation system vs increase in cost while converting from temporary to permanent.
- would 8" thick planks support lateral load on the long term with the help of soldier pile work rather than original 12"
- would a 12" section soldier pile be able to take vertical loads from the system and transfer it to say 36" sockets embedded 10' into very dense saprolitic soil.
The new idea is to make the SOE as permanent, that is to make the soldier piles and timber lagging take the short term loads and then after the excavation is done the reinforced concrete basement wall will be cast in place between soldier piles and becomes as lagging to the long term permanent system. there will be a beam runs on top of the soldier piles and the concrete planks which will provide support for the 2 story loads.
I am trying to compare the two systems:
system (1) temporary shoring system with 12" thick basement wall and basement wall footings
system (2) permanent shoring system with 8" thick basement wall and not basement footings
Note: No tiebacks permitted since there is a nearby basement wall of structure runs 4' away along the property line.
- Do you think there is any savings in foundation system vs increase in cost while converting from temporary to permanent.
- would 8" thick planks support lateral load on the long term with the help of soldier pile work rather than original 12"
- would a 12" section soldier pile be able to take vertical loads from the system and transfer it to say 36" sockets embedded 10' into very dense saprolitic soil.