radgo
Civil/Environmental
- Feb 16, 2003
- 1
I am installing a soldier pile wall. 3/8 inch sheet steel seam welded is specified for the caisson (36 inches in diameter) which is 15 feet in drilled earth to hold concrete in which half the pile will be embedded. The owner representative will let us pull the caisson and reuse it. I think this presents constructability problems, however, and wish to use 16 gauge corrugated metal pipe left in place as a substitute. The rep has asked for a specification that allows this optional approach. Can anyone recommend a source for this spec? Thank you.