1
- #1
DSKENGR
Structural
- Jun 30, 2014
- 8
I'm designing a soldier pile and lagging retaining wall. There is an existing building (2 story house) that will be near the wall (1 to 2ft from the back). I plan to design the wall with an appropriate surcharge from the house foundation and limit the deflection of the top of the wall to reduce potential settlement. What should the maximum settlement be? And also, is there any need for underpinning in addition to the wall and/or should I sequence the drilling operation to alternate piles (i.e., every other pile installed first) to reduce the settlement potential?