GeotechNerd86
Civil/Environmental
- Dec 5, 2019
- 2
I am writing this thread from Africa and have seen that Multi-anchored Soldier Piles (Concrete and shotcrete lagging) are used extensively in places such as Melbourne.
I have a few questions and was hoping someone from there would be so kind to respond:
- AS4678 does not provide clarification on how you should look at the required anchor forces (Assuming we are using LE methods). Do you use equivalent earth pressures(Terzaghi and Peck or FHWA?) and specify anchors with similar tieback forces and structural capacity with increase in depth? I assume this is then checked in FE or with Beam on Elastic Methods to confirm the requirement?
- Do you use equivalent earth pressures to derived Bending Moments in the piles or other methods? And then check these in FE or BOE?
- Do you use post injection grouting to increase the bond strength of the ground anchors?
- I see you also leave gaps in your shotcrete lagging, why don't you just but the permanent slabs up against the wall? What is the reasoning behind tieing the slab to the wall?
- Do you have high ground watertables and do you dewater site or wont you use Soldier Piles in such cases?
- Why the need for a capping beam before you excavate? We normally only construct this once we reach the ground slab?
Thanks so much
GeotechNerd
I have a few questions and was hoping someone from there would be so kind to respond:
- AS4678 does not provide clarification on how you should look at the required anchor forces (Assuming we are using LE methods). Do you use equivalent earth pressures(Terzaghi and Peck or FHWA?) and specify anchors with similar tieback forces and structural capacity with increase in depth? I assume this is then checked in FE or with Beam on Elastic Methods to confirm the requirement?
- Do you use equivalent earth pressures to derived Bending Moments in the piles or other methods? And then check these in FE or BOE?
- Do you use post injection grouting to increase the bond strength of the ground anchors?
- I see you also leave gaps in your shotcrete lagging, why don't you just but the permanent slabs up against the wall? What is the reasoning behind tieing the slab to the wall?
- Do you have high ground watertables and do you dewater site or wont you use Soldier Piles in such cases?
- Why the need for a capping beam before you excavate? We normally only construct this once we reach the ground slab?
Thanks so much
GeotechNerd