joe26
Geotechnical
- Feb 5, 2015
- 4
Hi everyone,
I am a geotechnical EIT and I have been asked to design a temporary shoring for an excavation depth of 10 feet below the existing ground surface. The owner and contractor have insisted on using helical piles as soldier piles with wood lagging. The geotechnical report says that there is very dense mixture of till, silt and clay down to 4 feet below the existing grade and compact sand below that. It also says that minor seepage was encountered in the sand layer. I do not have a lot of experience designing shoring systems so any help would be appreciated. I started using the California trenching and shoring manual and I believe it offers some good advice. I was however not able to compute the embedment depth required below the dredge line. Also the helical piles that are to be used have a circular section (5.6" dia).
I am a geotechnical EIT and I have been asked to design a temporary shoring for an excavation depth of 10 feet below the existing ground surface. The owner and contractor have insisted on using helical piles as soldier piles with wood lagging. The geotechnical report says that there is very dense mixture of till, silt and clay down to 4 feet below the existing grade and compact sand below that. It also says that minor seepage was encountered in the sand layer. I do not have a lot of experience designing shoring systems so any help would be appreciated. I started using the California trenching and shoring manual and I believe it offers some good advice. I was however not able to compute the embedment depth required below the dredge line. Also the helical piles that are to be used have a circular section (5.6" dia).