Hi
Pouring 5000 sq ft 6" slab in basement. Using W4xW4-4x4 WWF mesh (plus fiber). Need to purchase plastic chairs for the mesh . . . have a hunch I need 1 per 4 sq ft . . . 1250 chairs . . . the concrete will be pumped . . . believe the crew will operate from plywood over the mesh . . . just moving back the plywood back as they progress.
So what is the correct spacing for the chairs and mesh?
Thank you,
Larry
Pouring 5000 sq ft 6" slab in basement. Using W4xW4-4x4 WWF mesh (plus fiber). Need to purchase plastic chairs for the mesh . . . have a hunch I need 1 per 4 sq ft . . . 1250 chairs . . . the concrete will be pumped . . . believe the crew will operate from plywood over the mesh . . . just moving back the plywood back as they progress.
So what is the correct spacing for the chairs and mesh?
Thank you,
Larry