structure567
Civil/Environmental
- Nov 12, 2013
- 50
I have a question regarding the use of Mud Mat to meet the design excavation level.
I am working on a deep foundation that is laying on slightly to none weathered bedrock. The excavation involved blasting which resulted in some areas that were over excavated approximately 5 feet below the design elevation in which the foundation is suppose to sit on.
We will be filling the gap with 3000 psi concrete acting as a mud mat. I'm trying to find out if there are any specific standards to follow for the design of mud mat. Although this concrete is purely acting as filler for overexcavated areas, it is still pretty thick for a blinding layer and will be poured in an area that will have water due to the high water table.
I am working on a deep foundation that is laying on slightly to none weathered bedrock. The excavation involved blasting which resulted in some areas that were over excavated approximately 5 feet below the design elevation in which the foundation is suppose to sit on.
We will be filling the gap with 3000 psi concrete acting as a mud mat. I'm trying to find out if there are any specific standards to follow for the design of mud mat. Although this concrete is purely acting as filler for overexcavated areas, it is still pretty thick for a blinding layer and will be poured in an area that will have water due to the high water table.