Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations GregLocock on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Specification for Organic Content in Fill 1

Status
Not open for further replies.

DougB

Geotechnical
Feb 14, 2003
5
What do you consider a reasonable maximum organic content to specify for engineered fill placed under a building foundation? Material in question is a silty clay bordering on a silt. I am expecting 0 to 6 feet of fill under the footings (ie depth varies). 2 story wood frame construction for condominiums.
 
Replies continue below

Recommended for you

We traditionally recommend NOT using soil with more than 4% organics for engineered fill.
 
Thanks. Material in question came in at 3% and I was thinking a 2% limit was too strict but 5% seemed a bit too lax. So that 4% limit works for me. I'll consider your response standard of practice :). Kidding. But if anyone else has a comment I'd be interested.
 
DougB,

We generally recommend 3% max by dry weight. Obviously, no large organics (stumps, branches, roots, leaves, lumber or construction debris, etc.).

Jeff


Jeffrey T. Donville, PE
TTL Associates, Inc.
 
DougB - why use a silty clay borderline silt as structural fill below a foundation? Wouldn't a granular material be a better choice (for compaction and sturctural capacity). Silt and silty clay are highly moisture sensitive and depending on the location of the job, the contractor could have serious compaction problems if the jobsite gets wet. Of course, a good contractor could make the material work, but I've learned to plan for the worst case scenario (i.e., low bidder!j/k).
 
I agree with the 3% under footings and maybe up to 6% under slabs that could tolerate a little settlement and cracking.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor