shekar1188
Civil/Environmental
- Feb 23, 2005
- 1
We are GC compant doing a project for USACE. We are casting concrete cylinder spceimens for 7 and 28 day breaking. The specification calls for curing the specimens as per ASTM C31. ASTM C31 suggests curing to be done in temp 60 -80 F, also gives an option for field curing.
Under these condition, please advise which method should be used. The specification not say anything about field curing.
The USACE rep thinks it should be field cured atleast for 7 days. Which spec does not mention nor ASTM C31.
The testing lab thinks that it should transfered to lab after initial setting of 3 days.
regards
Under these condition, please advise which method should be used. The specification not say anything about field curing.
The USACE rep thinks it should be field cured atleast for 7 days. Which spec does not mention nor ASTM C31.
The testing lab thinks that it should transfered to lab after initial setting of 3 days.
regards