TravisMack
Mechanical
- Sep 15, 2003
- 1,757
Question on stages and hose valves.
Project in question has a proper stage that requires hose valves. In the past, I have just supplied them from the overhead system in the area (always coming off a 4" main). I have always included 50 gpm inside hose allowance for each valve combined with the overhead sprinkler calculations for the area. Additionally, I will calc them to provide 250 gpm each at 100 psi using the FDC as the water supply as if it were a true standpipe system.
I currently have a reviewer that is stating we have to add 250 gpm each interior hose allowance and add that to the sprinkler system. He is not asking for any specific pressure, just 250 gpm each, so we essentially have 500 gpm inside hose. When you combine this with the OH2 flows for the stage, you are looking at flowing just over 800 gallons through the system. The other option he gives is to supply them from an adjacent system. This will require running about 400' of 4" piping through the school. He states that if we supply them from an adjacent system, we do not need to add the hose allowance to the calcs.
I have sent the question to the AHJ, but I have not heard back yet. I think they are off on Fridays so I won't hear for a few days. What are your thoughts on how these hose valves are to be supplied and calculated?
Travis Mack
MFP Design, LLC
"Follow" us at
Project in question has a proper stage that requires hose valves. In the past, I have just supplied them from the overhead system in the area (always coming off a 4" main). I have always included 50 gpm inside hose allowance for each valve combined with the overhead sprinkler calculations for the area. Additionally, I will calc them to provide 250 gpm each at 100 psi using the FDC as the water supply as if it were a true standpipe system.
I currently have a reviewer that is stating we have to add 250 gpm each interior hose allowance and add that to the sprinkler system. He is not asking for any specific pressure, just 250 gpm each, so we essentially have 500 gpm inside hose. When you combine this with the OH2 flows for the stage, you are looking at flowing just over 800 gallons through the system. The other option he gives is to supply them from an adjacent system. This will require running about 400' of 4" piping through the school. He states that if we supply them from an adjacent system, we do not need to add the hose allowance to the calcs.
I have sent the question to the AHJ, but I have not heard back yet. I think they are off on Fridays so I won't hear for a few days. What are your thoughts on how these hose valves are to be supplied and calculated?
Travis Mack
MFP Design, LLC
"Follow" us at