Regarding Required Installations for Standpipe,IFC 905.3.1 states Height. Class III standpipe systems shall be
installed throughout BUILDINGS where the floor level of the
highest story is located more than 30 feet....
My question is this 905.3.1 only applies to buildingS , am i right?
A open process structure in chemical plant often is very high, but they are not buildings, are not required to installed the standpipe CLASS III per as 905.3.1.
open process structure in chemical plant often is equiped with 1 1/2 or 1 1/4 standpipe and hose reel under company's standard for incipient fire . I learn that some open process structures of BASF's chemical pant in Louisiana is being installed with class I(with 2 1/2 hose valve)standpipe for fire trucks to hook up. i am just wondering if they are required by local fire code.
Does someone have some acknowlede of this. i really apreciate the reply. Thanks!
installed throughout BUILDINGS where the floor level of the
highest story is located more than 30 feet....
My question is this 905.3.1 only applies to buildingS , am i right?
A open process structure in chemical plant often is very high, but they are not buildings, are not required to installed the standpipe CLASS III per as 905.3.1.
open process structure in chemical plant often is equiped with 1 1/2 or 1 1/4 standpipe and hose reel under company's standard for incipient fire . I learn that some open process structures of BASF's chemical pant in Louisiana is being installed with class I(with 2 1/2 hose valve)standpipe for fire trucks to hook up. i am just wondering if they are required by local fire code.
Does someone have some acknowlede of this. i really apreciate the reply. Thanks!