2ply
Industrial
- Aug 4, 2015
- 11
I was wondering in anyone has experience with the start up procedure of propane vaporizers. I have an issue with the heat load at start up. The vaporizer is for 25000 kg/hr super-heated propane @ 25 bar. LP steam is used as heat transfer input with condensate side control.
Start up load seems to be very load for this...Peak load is 4.5MW and start up has a very small load plus gas sent to flare.... How is it usually done?
Start up load seems to be very load for this...Peak load is 4.5MW and start up has a very small load plus gas sent to flare.... How is it usually done?