Hello,
Our local code limits footing settlement to 1 inch and mat settlement to 2 inches.
The same way there are static settlement limits for footings and mats, are there any for post-liquefaction settlement?, or when are post-liquefaction settlements considered to be ok or too high?
To my knowledge there is no relationship between static settlement and post-liquefaction settlement.
Our local code limits footing settlement to 1 inch and mat settlement to 2 inches.
The same way there are static settlement limits for footings and mats, are there any for post-liquefaction settlement?, or when are post-liquefaction settlements considered to be ok or too high?
To my knowledge there is no relationship between static settlement and post-liquefaction settlement.